“Cellarbrations” are open for business! Visit instore to get you favourite drop soon!

Greenvale Shopping Centre is exanding!

You may have noticed some building activity in the carpark off Greenvale Drive recently. This is the start of an exciting expansion to Greenvale Shopping Centre.

The Centre extension will commence in end-October 2024 and conclude mid-July 2025 and will see the addition of 1200m2 to the Centre featuring new retail and leisure offers.

The works will be done in two major stages:

Stage 1: end-October to mid-December

    • Works in the large ORANGE zone include resurfacing of the driveway and relocation of underground services. Customer parking bays in this section will NOT be available during this time.
    • The smaller ORANGE zone will see closure of the footpath from Mstr Dough to the Coles late trade entrance. There will be a small number of carparking bays unavailable for use in this area.
    • Coles late trade entrance will remain operational during these works with pedestrian access via the ramp to the north of the Greenvale Drive carpark. Some closures will be required from time to time.
    • Duration of Stage 1 works – approx. 6 weeks
    • All carparking bays impacted during this stage will reopen before Christmas.
  •   
  • Stage 2: mid-Jan 2025 to mid-July 2025
    • Works in this stage include excavation of existing carpark, piling and slab pour for new carpark, suspended slab, steel, roofing and façade works
    • The carparks highlighted in the ORANGE zone will be unavailable for the duration of Stage 2 works
    • Greenvale Drive entrance will be operational
    • Customers will need to park in main carpark off Mickleham Road
    • Coles late trade entrance will remain operational during these works with some closure required from time to time